Budgeting Time And Value Risk Management

 

Analyze the project plan of a payroll system that is behind schedule and over budget. The project was supposed to be completed in one year, but now it is running about three months behind schedule and 25 percent over budget. It is expected that the project may continue to fall further behind schedule and over budget. Your superior wants to know if the project can be saved.

Recommend a series of actions to save the project, and identify the risks in taking such an approach.

Sample Solution

Unfortunately, analyzing the project plan without access to it directly is impossible. However, I can offer a general framework to diagnose the situation and propose potential solutions.

Current Situation:

  • Delay: 3 months behind schedule
  • Budget overrun: 25% over budget
  • Further delays and overruns expected: This suggests underlying issues requiring immediate attention.

To assess the project’s salvageability, we need answers to these questions:

  1. Root Causes: What are the specific reasons for the delays and overruns? (Scope creep, technical issues, poor planning, resource constraints etc.)
  2. Project Goals: Are the original goals still achievable or do they need adjustment?
  3. Stakeholder Support: Are stakeholders (management, users) still committed to the project and willing to absorb challenges?
  4. Project Dependencies: Does the project impact other critical operations, and what are the consequences of further delays?

Once you have this information, you can:

1. Conduct a Risk Assessment:

  • Identify all potential risks associated with continuing the project (e.g., further delays, costs, legal issues, employee morale).
  • Evaluate the likelihood and impact of each risk.
  • Develop mitigation strategies for the most significant risks.

2. Develop a Recovery Plan:

  • Prioritize tasks: Focus on essential functionalities to deliver a minimally viable product (MVP) on time and within budget.
  • Cut non-essential features: Delay or eliminate features that contribute minimally to core functionality.
  • Optimize resource allocation: Ensure resources are focused on critical tasks and eliminate redundancies.
  • Implement stricter change control: Prevent scope creep and manage changes effectively.
  • Improve communication: Transparent communication with stakeholders is key to managing expectations and securing buy-in.

3. Evaluate Feasibility:

  • Based on the risk assessment and recovery plan, determine if salvaging the project is feasible. Consider:
    • Cost of recovery vs. starting over: Analyze the financial implications of both options.
    • Time constraints: Are there external deadlines that make recovery impossible?
    • Team morale: Can the team recover from the setbacks and deliver effectively?

Risks of Continuing:

  • Failure to meet revised goals: The recovery plan might not be enough to catch up.
  • Further cost overruns: Unexpected challenges during recovery could escalate costs.
  • Demotivation and burnout: Continued delays and pressure can impact team morale and performance.
  • Reputation damage: Unsuccessful recovery could damage the organization’s reputation and stakeholder trust.

Remember:

  • This is a complex situation requiring careful analysis and stakeholder involvement.
  • Seek expert advice from project management professionals for in-depth guidance.
  • Clearly communicate the risks and potential outcomes to all stakeholders before proceeding.

Conclusion:

Saving a troubled project requires a swift and decisive response. By understanding the root causes, prioritizing tasks, and managing risks effectively, you can increase the chances of success. However, transparent communication and realistic expectations are crucial throughout the process. Good luck!