Project 1
You are a homeowner and have a project that you want accomplished in the next month. Today is Wednesday, the 26th of August. You have guests arriving on Friday the 25th of Sept. You must have the project completed by then. You work full time during the day, that gives you 4 weekends to accomplish the task.
You want to stain and seal a total of 4 concrete pads: 3 concrete pads (6’ X 8’ each) around your 3 sets of wood stairs to your wrap around wood porch, as well as a larger concrete pad (8’ X 15’), also with wood stairs, that you use for storage but someday you will install a spa on the pad.
Put together a Project Plan for the Project. (see Chapter 4, 5 & 6)
1)Define the Project Scope.
2)Establish the Project Priorities.
3)Create the Work Breakdown Structure (WBS).
4)Create a Project Communication Plan (will be minimal for this project).
5)Draft Project Plan, including schedule and resource requirements. A MS Project Gantt Chart is required. All MSU UIT computers have MS project loaded on them. You will need to schedule time to input the information into MS Project. (NOTE: Connect.mheducation.com site has MS project videos and tutorials to help you with this part of the project).
6)Complete the Project Scope, Project Priorities, WBS, Communication Plan and Draft Project Plan complete by 9 Sept. Turn in to Assignments Project 1 in D2L.
7)Project closeout report including planned vs. actual results, and opportunities for improvements in future projects will be completed later. (Note: you will have to make up a scenario that occurred as this is not a project that you actually did. Document the “actual” work so I can refer to it in the report.) Hand in to D2L in Assignments Project 1, due Wed. midnight, Sept. 23.
Boundary Conditions:
1)You and your significant other have agreed to budget $500 to do this project.
2)You do NOT own a pressure washer.
3)You do not currently own any equipment for delivering paint or liquids.
4)You have some local college students that help you out from time to time for $15/hr. They are usually available on weekends but do have exams, etc. that compromise their availability.
5)Your significant other doesn’t like to, nor does help, on these type of projects.
6)You can shop for materials during the evenings of the week, but you are only able to work on the weekends. Because of a history of back issues you can only work 8 hours in any one 24 hour period.
I will give you some input on the 10th of September. It will have an impact on your project. You will make note of the impacts in your closeout report.
Reference material for concrete cleaning, staining, and sealing.
DIY Pete (this guy is from Bozeman!): https://www.youtube.com/watch?v=ZSlzelQYEOU
http://toolboxdiy.com/category/how-to/This is the do it yourself main website. Go down a bit to find the videos on cleaning, stain and sealing the concrete slab.
Rough sketch of house outline and location of 4 concrete pads.
the individuals may want to ensure that they perform well because they will not want humiliation of their “failures” or poor results being publically announced to the firm. In spite of this, it can be a cause of demotivating staff that were not achieving as well as others in the organisation due to the fact that they may be feel humiliated from public announcements.
Another reward system that GCS have in place is the commission based paying system, the consultants will be paid commission on the gross margins between the price charged to the client and what GCS paid the contractor (King, Chung & Hunter, 2014). This will motivate the staff in wanting to make sure that they achieve a large gross margin to receive more commission (King, Chung & Hunter, 2014). Both of these reward systems will link with the operational excellence and ensure that the company achieve their business goals because both reward systems are a way of which the firm motivates their staff to hit business goals and ensuring that they are providing a high level service to their clients.
The staffing and reward systems show a strong sense of GCS using a strategic-fit approach framework within their business model to achieve the operational excellence. Both of the HR practices fitted in with the vertical fit of the firm in order to help the organisation gain competitive advantage and market share. As well as fitting the horizontal fit of ensuring that each practice aligned with one and other in order to work in harmony, recruiting the correct staff lead to higher possibility of staff reaching goals and therefore receiving rewards from GCS. In spite of this, there are still areas in which GCS need to improve their HR practices to increase their productivity, performance and competitiveness within the market.
GCS uses a variety HRM practices such as 360-degree recruitment, reward based s