1) Which project role provides resources or support for the project, promotes and protects the project at
higher levels of management, and takes an active role in the project from the chartering stage through
project closure?
a) Functional manager
b) Project manager
c) Project team member
d) Project sponsor
2)Which PMBOK® Guide Knowledge Area includes those processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully?
a) Cost management
b) Scope management
c) Risk management
d) Quality management
3) In order to be successful, the project team must be able to assess the needs of stakeholders and manage their expectations through effective communications. At the same time they must balance competing demands among project scope, schedule, budget, risk, quality, and resources, which are also known as project _____?
a) Plan elements
b) Deliverables
c) Constraints
d) Targets
4) Projects pass through a series of phases as they move from initiation to project closure. The names and number of these phases can vary significantly depending on the organization, the type of application, industry, or technology employed. These phases create the framework for the project, and are referred to collectively as the ________.
a) project life cycle
b) project management information system (PMIS)
c) product life cycle
d) Talent Triangle
5) Based on PMI’s definition, which of these is a good example of a project?
a) manufacturing a standard commodity
b) following policies and procedures for procuring an item
c) designing and launching a new website
d) using a checklist to perform quality control

6) When would a predictive project life cycle be the preferred approach?
a) when the high-level vision has been developed, but the product scope is not well defined
b) when the environment is changing rapidly
c) when the product to be delivered is well understood
d) when the product will be created through a series of repeated cycles
7) To be effective, a project manager needs to possess all of the following competencies except ____.
a) personal effectiveness—attitudes, core personality traits, leadership

 

Sample Solution

lican Party’s foundation incline more towards an abolitionist subjection plan. Conservatives saw subjugation as indecent and disallow the extension of bondage into every single western domain, they go against the confirmation of new slave state and constrained a definitive eradication of servitude. The Republican faction was to a greater degree a Northern state ideal party, they had the very ethics that the party did. Nonetheless, the South goes against the Republican coalition. Stephan Douglass was in the progressive alliance, which was the generally #1 by the South. The Southerners saw the Republican faction as progressive association, since it compromised their lifestyle and their property privileges. The intriguing reality here is that the Southern States undermine with severance even before Lincoln won the official political race.

The Civil War endured (1860-65) slaves-states see the start of a Northern Revolution, start a counter-transformation. South Carolina chose to withdrew from the Union and the requests to the state right way of thinking to leave the association. This lead to the arrangement of the Confederate States of America. The Confederacy-South Carolina, Georgia, Florida, Mississippi, Louisiana, Alabama and Texas. The President of the Confederate states was Jefferson Davis. The Spark of war, was the issue of the Federal fortifications in the Confederate States, Fort Sumter in South Carolina. The Confederate states were known for their extraordinary military abilities under the standard Robert E. Lee, and the General which drove the Union to triumph. De-centralization thwarted the alliance’s capacity to arrange the conflict endeavors. Such state’s privileges, A.) failure to raise assets through charges confederate states opposed tax collection B.) powerlessness to pass induction regulations, the confederate states battled all alone. The South needed adequate harvest utilization horticulture and wasteful transportation framework. There was restricted railroad lines accessible the south had 9,500 miles versus 22,000 miles for the North.

The contention about the South was about the versatility. The South was not such presented to railroad tracks however much the North was. Since they didn’t have the portability like the

This question has been answered.

Get Answer
WeCreativez WhatsApp Support
Our customer support team is here to answer your questions. Ask us anything!
👋 Hi, Welcome to Compliant Papers.